What to Expect During Spray Booth & Oven Installation
- Feb 4
- 3 min read
Description
Installing a spray booth or curing oven is not just a delivery—it’s a coordinated construction, mechanical, and commissioning process. One of the most common questions we hear is “How long will installation take?” Closely followed by “What should we expect during install?”
The reality is that installation timelines depend heavily on preparation, system complexity, and site conditions. Understanding the installation phases—and where delays typically occur—helps shops plan downtime, coordinate trades, and avoid surprises.
This article breaks down what happens during a typical spray booth or oven installation and explains realistic timelines based on real-world projects.

Spray booths and ovens are integrated systems involving airflow, heating, electrical, controls, and safety considerations. Installation generally happens in phases, each with its own requirements and dependencies.
Phase 1: Site Preparation (Often the Biggest Variable)
Before equipment ever arrives, the facility must be ready.
This typically includes:
Adequate floor space and clearances
Confirmed ceiling height and roof structure
Electrical service sized and stubbed
Gas service (if applicable) brought to location
Concrete pads or floor prep completed
Permits approved or in progress
Typical timeline:• A few days to several weeks, depending on facility readiness
Most installation delays occur here—not during equipment assembly.
Phase 2: Equipment Delivery & Staging
Once equipment arrives onsite, it is staged near the install location. This phase is often overlooked but critical for efficiency.
Considerations include:
Forklift or crane access
Indoor vs. outdoor staging
Protection from weather and damage
Sequencing of components
Typical timeline:• 1 day
Proper staging can significantly reduce assembly time.
Phase 3: Mechanical Assembly
This is where the booth or oven physically takes shape.
For spray booths, this includes:
Panel and structural assembly
Plenum and filter bank installation
Fan and duct connections
For ovens, this includes:
Panel assembly and sealing
Burner or heater installation
Exhaust and relief ducting
Typical timeline:• Spray booth: 4–5 days• Batch oven: 4–7 days• Conveyor or large oven systems: 1–2+ weeks
System size and customization level have a great impact here and can strongly influence installation times.
Phase 4: Electrical, Gas & Controls Integration
Once the mechanical structure is in place, utilities and controls are connected.
This phase includes:
Electrical wiring to fans, heaters, and controls
Control panel installation
Gas piping and leak testing (if applicable)
Safety interlocks and sensor integration
Typical timeline:• 1–3 days for smaller systems• Several days for complex or automated lines
Coordination between trades is critical at this stage.
Phase 5: Startup, Balancing & Commissioning
Installation is not complete when the booth or oven turns on. Proper commissioning ensures the system performs as designed.
This phase typically includes:
Airflow verification and balancing
Temperature calibration
Safety system checks
Control logic verification
Operator walk-through and training
Typical timeline:• 1–2 days
Skipping or rushing this step often leads to long-term performance issues.

Total Installation Timeline: What’s Realistic?
While every project is different, typical timelines look like this:
Small to mid-size spray booth: 1–2 weeks total
Large or custom spray booth: 2–4 weeks
Batch oven: 1–2 weeks
Conveyorized or integrated finishing line: 3–6+ weeks
These ranges assume proper site preparation and coordinated trades.
What Impacts Installation Time the Most
Key factors that extend timelines include:
Incomplete site prep
Utility upgrades discovered late
Permit or inspection delays
Complex duct routing
Custom controls or automation
Conversely, well-prepared sites with clear scope and experienced installers often finish ahead of schedule.

How California Pulse Helps Reduce Installation Risk
At California Pulse, installation success starts long before equipment ships. Our process includes:
Clear installation drawings and requirements
Code-conscious system design
Support during mechanical and electrical integration
Startup guidance to ensure proper performance
The goal is not just fast installation—it’s correct installation that delivers long-term performance.
Installing a spray booth or oven is a manageable, predictable process when expectations are clear and preparation is thorough. Understanding the installation phases and realistic timelines helps shops plan production, reduce downtime, and avoid costly delays.
The right equipment, combined with proper planning, turns installation from a disruption into a smooth transition.





Comments